Turning electrical energy into heat in a controllable manner - how does the load box "burden" the generator, UPS and computer room busbar? Why is the power switched in steps instead of continuously adjustable? How to choose between air cooling and liquid cooling? This article talks about the principles and selection, and uses Yinlang’s own series of rack-mounted load boxes to compare them one by one.

1. What exactly does the load box do?

In a word: a device that can controllably convert electrical energy into heat.

For equipment such as generator sets, UPS, transformers, and energy storage converters, the power marked on the nameplate is "design capacity" and does not equal "actual capacity." The true output capability must be measured under load: whether the voltage and frequency are stable at full load, whether the temperature rise will exceed the limit, and whether there will be power loss during the switching process. But real loads (servers, air conditioning, lighting) can't be added and subtracted as often as you want during the acceptance phase - and real equipment won't allow you to repeatedly push it to its limits.

The load box solves exactly this problem: it turns all electrical energy into heat and dissipates it, the power can be set accurately and in steps, and it can run stably for a long time. So it is both a "test device" and a typical dummy load.

In the data center, this step usually occurs during the system joint commissioning (IST) stage: first, use a dummy load to gradually load the entire power supply and distribution link (mains - transformer - low-voltage cabinet - busbar - head cabinet - cabinet) to the designed capacity, confirm that there are no bottlenecks, and then move in the real IT equipment.

Generator sets may also be subject to applicable standards and project acceptance requirements. Confirm load-test frequency, duration and loading conditions from the generator type, application, adopted standard and edition (such as NFPA 110 where applicable), together with manufacturer and project requirements. No single percentage or duration should be treated as a universal requirement for all emergency/standby generators. Load banks can support the corresponding routine or acceptance tests.

2. Resistive, inductive and capacitive: three "load properties"

Load boxes are divided into three categories according to the load properties they can simulate:

Typepower factormock objectMain verification
Resistance (R)PF = 1.0Heating, lighting, traditional IT loadsActive output capacity, engine and cooling
Sensibility (L)About 0.8 lagMotors, transformers, water pumpsVoltage regulation and excitation capabilities
Capacitance (C)Ahead of timeSwitching power supply IT loadUPS/Bypass with capacitive load capability

A load bank with one load characteristic covers only that testing dimension. To simulate different power factors, resistive, inductive and capacitive modules can be combined for the target range. Achievable power factors, power levels and operating conditions must follow the specific model’s specifications and controls.

Rack mount load banks are overwhelmingly resistive. The reason is very practical: What needs to be verified in the computer room scenario is "whether this power supply link can safely send power out and whether heat energy can be discharged." This is essentially an active power issue. A resistive load with PF=1 is the most straightforward, easiest to calculate, and the cheapest and most reliable.

3. Why is it made “rack-type”?

Load boxes come in two forms. One is centralized - boxed or trailer type, with power ranging from hundreds of kW to MW level, placed outside the computer room and introduced with large-section cables.

The other is the rack type: a single unit has a few kW to dozens of kW, is made into a standard rack size, and is directly pushed into the cabinet. Its value is not in power, but in location:

  • Access nearby. Which row of cabinets the dummy load is placed can determine which row of branch circuits. The capacity and balance issues of shunt busbars, row cabinets, and cabinet PDUs will only be exposed if the loads are placed in the corresponding locations.
  • The wind channel is real. The fan and heating element of the rack load box are in the cabinet, and the heat it generates travels through the real hot channel. Cold aisle temperature, return air temperature, and local hot spots can all be measured according to real working conditions.
  • Can be loaded in batches and step by step. By adding them row by row, you can see how the voltage, current, and temperature change as the load increases.
  • Save space. In computer rooms where space is tight, the rack type can directly utilize the existing cabinet space.

The price is that the power of a single machine is small, and many units are needed to achieve the same total power; and dozens of units are running at the same time, which requires higher power distribution capacity and noise management.

4. What’s in a rack load box?

4 kW AC rack-mounted load bank, front view
Figure 1 | 4 kW AC rack load box. On the front panel are the LCD meter, fan and four-way load gear switch, temperature alarm (red) and work prompt (green) indicator lights; there are rack handles on both sides, and honeycomb vents on the front and rear.

Taking the front panel apart, there are not many elements, but each item corresponds to an engineering problem:

  • Resistive element - metal tube/wirewound power resistor, responsible for turning electrical energy into heat. This is the real heart of the load box.
  • Fan and air duct - forced air cooling takes away the heat from the resistor. The "fan" on the panel occupies a separate switch, indicating that the fan is an independent circuit: usually start the fan first, confirm that the air path is normal, and then put the load on.
  • Gear switch - each load is equipped with a circuit breaker, corresponding to a fixed power level. This 4 kW model is 0.5 / 1.5 / 1 / 1 kW quad.
  • Display - LCD or digital meter displays real-time voltage and current, making it easy to check while loading.
  • Protection and indication: check whether the specific model provides temperature alarms, operating indication, fan-failure detection and overtemperature shutdown, and validate the trip conditions. Permission for extended unattended operation must also be confirmed against manufacturer instructions and site management requirements.
  • Rack structure - standard rack width, handles on both sides, easy to push into the cabinet and carry.

5. How is the power “cut”?

This is the core operating logic of the load box.

Load-bank power is usually adjusted by combining multiple steps, each switched by a circuit breaker or contactor. Available power settings depend on the actual step configuration. Select combinations according to panel instructions and model specifications; stepped adjustment does not mean every continuous power value can be achieved.

Why aren't the gears divided into equal parts? Because equal division will require a very large number of switches to produce fine power. Using this weighted combination of 1 : 2 : 4 : 8, n switches can obtain 2ⁿ power points, and the resolution is equal to the smallest one. It’s very clear when you look at the panel of the Yinlang model:

ModelPanel geartotal
6 kW ACFan + 500 W / 1.5 kW / 1 kW / 3 kW6 kW
12 kW ACFan + 1 / 1 / 2 / 4 / 4 kW12 kW
16 kW ACFan + 500 W / 500 W / 1 / 2 / 4 / 4 / 4 kW16 kW
48 kW AC/DC liquid coolingThree phases each 1 / 2 / 3 / 4 / 6 kW3 × 16 = 48 kW
16 kW AC rack-mounted load bank, front view
Figure 2|The gear layout of the 16 kW model: A / B / C / D four-group branching, the minimum gear is 500 W, and the maximum gear is 4 kW. The combination of seven load switches can produce any power between 0.5 kW and 16 kW in steps of approximately 0.5 kW. There are also power indication and high temperature alarm on the panel.

Manual models use circuit breakers for manual switching; models with controllers (such as the touch screen on the liquid-cooled model panel) can automatically load according to the set curve and record data through the Ethernet port or USB.

6. AC, DC and PTC

AC Resistive Load Box: The most common type. According to the number of phases and voltage, single-phase AC220 V, three-phase AC380/240 V, etc. For three-phase models, pay attention to evenly distribute the load to the three phases - the 48 kW model has three phases A / B / C of 16 kW each. The three phases are grouped independently on the panel to avoid single-phase overload.

DC load box: conducts discharge or load tests on energy storage batteries, DC bus bars, charging modules, and photovoltaic modules. Voltage levels such as DC380 V are common. When selecting, confirm the voltage level and polarity connection.

PTC load banks: PTC means positive temperature coefficient. The element’s resistance may rise substantially in a particular temperature region, reducing current. Confirm this characteristic from the specific element and model data. It does not replace overtemperature, fan-failure or other necessary protection, and PTC construction alone cannot guarantee system safety if control fails. Extended operation must follow model instructions and be validated under actual cooling conditions.

12 kW AC/DC rack-mounted load bank, front view
Figure 3|12 kW rack-mounted model (AC and DC), the panel has five-way gears of 1 / 1 / 2 / 4 / 4 kW, equipped with power indicator and high temperature alarm.

7. Air cooling or liquid cooling

Where the heat ultimately goes determines how much power a single machine can do.

Air cooling: relies on a fan to discharge hot air into the computer room. The structure is simple and does not require external piping; however, the power density is limited (a single machine usually has a few kW to more than ten kW), and the hot air discharged will directly increase the load of the air conditioner in the computer room, and the noise is not small when dozens of units are turned on at the same time.

Liquid cooling: The heat of the resistor is transferred to the cooling water and taken away by the water system. The same volume can carry much higher power, and the heat is not discharged in the computer room, and the noise is much lower.

48 kW AC/DC liquid-cooled load bank, front view
Figure 4|48 kW AC/DC liquid cooling model. There is a touch screen, emergency stop button, power indicator, RJ45 network port and USB interface on the front; the A / B / C three phases are independently grouped, each phase has five-way gears of 1 / 2 / 3 / 4 / 6 kW, totaling 48 kW.

Adding liquid cooling to the rack type is a balance between "power density" and "not discharging heat to the computer room": it not only retains the benefits of the rack type's nearby access, but also makes up for the high power aspect.

8. What should you confirm one by one when selecting a model?

  • Voltage and number of phases: single-phase or three-phase, AC220/240 or AC380; for DC models, please confirm the voltage level and wiring method.
  • Total power and minimum gear: The total power determines how large a scale can be measured, and the minimum gear determines how precise the load can be.
  • Accuracy and temperature drift: the deviation between nominal power and actual power, and the change in resistance with temperature. When running continuously for a long time, temperature drift will directly affect the actual loading power.
  • Working system: continuous operation or intermittent operation, directly determines the cooling solution and available power section.
  • Size and installation: The height of the rack (3U / 4U / 6U, etc.), depth, and whether the air is from the front or the rear must match the air duct of the cabinet.
  • Direction of heat dissipation: Air cooling should reserve room air conditioning margin; liquid cooling should confirm water quality, flow rate, inlet and outlet water temperature, interface type and pressure drop.
  • Protection and monitoring: Whether over-temperature, fan failure, over-current, and phase loss protection are complete; whether host computer monitoring and data recording are required.
  • Site conditions: grounding, cable cross-section, upstream circuit breaker capacity, three-phase balance, noise limits.

Contact us to discuss your requirements